Work on the first 500-kilovolt power line to cross the advance excavation zone of the new Three Gorges shipping channel has entered its final stage, as crews relocate transmission lines to make way for the project. The aim is to restore power on schedule and keep clean electricity from the Three Gorges flowing without interruption.
According to Xinhua and the China Securities Journal, the line is a rebuilt section of the 500-kV Sanjiang second and third circuits in Taipingxi town, Yiling district, Yichang, Hubei province. Drone images taken on Nov. 15 showed workers from State Grid Hubei Ultra-High Voltage Company installing conductor fittings on a 100-meter tower, while wire-tensioning work over the channel construction site has continued in recent days.
광고 문의 · 300×25048 lines making way
The work is part of a relocation project for the Three Gorges power transmission corridor that began on June 8, the same day construction of the new channel started. Xinhua reported that because the channel will pass beneath existing high-voltage lines, 48 lines, including eight 500-kV trunk lines and 40 lines of 220 kV or below, must be moved to meet construction standards and future navigation requirements.
Under the plan, outages for high-voltage work are concentrated between October and the following April, and about 20 priority lines are to be relocated by the end of December. During the relocation, average daily transmission through the Three Gorges corridor is to stay above 300 million kilowatt-hours.
China News Service reported on Nov. 11 that the first relocated lines for the Gezhouba navigation expansion, the 220-kV Geyi and Gepo lines, had been re-energized and that temporary wharves at Gezhouba and Zhaojiagou had passed acceptance. Comprising the new Three Gorges channel and the Gezhouba expansion, the project is the first major national undertaking of the 15th Five-Year Plan and is described as the largest integrated project on the Yangtze's main stream since the Three Gorges Dam.