A fire broke out on the roof of an 18-storey building under construction in Taipei’s Beitou-Shilin Technology Park on the night of Nov. 22, spreading down to the 16th floor. Taipei asked New Taipei’s fire department for support, and the blaze was put out after about two and a half hours with no casualties.
According to the Central News Agency and the United Daily News, the Taipei City Fire Department received a report at 8:37 p.m. of a fire on the rooftop of a construction-site building near the junction of Fuguo Road and Chengping Road in Beitou District. The site is the ‘Lien Shang He Xu’ residential project, and flames shot up from rooftop scaffolding, lighting up the exterior. Firefighters evacuated workers on site.
광고 문의 · 300×250The fire started on the roof of the 18-storey building and at one point spread down to the 16th floor. By 10:30 p.m. five command vehicles, 27 fire engines, two ambulances, 102 personnel and a drone had been deployed, and New Taipei sent a 70-metre aerial ladder truck and three water tankers. The fire was extinguished at about 11:10 p.m.
Smoke model prompts stay-indoors advice
Using a smoke-dispersion model, the city government said smoke could affect Beitou and Shilin as well as Wugu, Luzhou, Tamsui and Bali in New Taipei, and urged nearby residents to limit outings, keep windows closed and wear masks outdoors. Air quality at the Shilin and Tianmu stations was still rated good at the time of reporting, and the environmental protection bureau said it would keep monitoring.
Police closed parts of Fuguo and Chengping roads so fire engines could park. Taipei Mayor Chiang Wan-an visited the scene, ordered an all-out effort and thanked frontline firefighters. The cause has not been determined, and fire officials will investigate once the scene is safe.
The technology park is being developed by Taipei as a hub for high-tech industry, with several large construction projects under way. After a string of fires at new high-rise sites in the greater Taipei area, calls are likely to grow for tighter checks on hot work and material management at late-stage sites.