Crews will tamp about 167 km of track and service 100 sets of turnouts after nearly five years of intensive operation and heavy rain took a toll on the line.
A large-scale concentrated overhaul has begun on the Boten-Vientiane stretch of the China-Laos Railway, the Laos section of the line. According to China Railway Kunming Group, work started at about 10 p.m. on November 15 around Vang Vieng and Vientiane South stations and is scheduled to continue until the end of December.
광고 문의 · 300×250The plan covers tamping on about 167 km of track and 100 sets of turnouts, adjusting them section by section to restore the original design standards and reinforce the track bed. Xinhua photographs showed crews working through the night near Vang Vieng station from the evening of November 18 to the early hours of November 20.
Four heavy maintenance machines sent abroad
The work uses Chinese-made heavy maintenance machines: two DWL-48 continuous tamping and stabilising vehicles and two CDC-16 turnout tampers. A 30-member overseas work team of skilled technicians is split into a track group and a turnout group working at different stations at the same time, an arrangement meant to keep disruption to traffic to a minimum.
The 1,035-km railway linking Kunming and Vientiane has run under high-density, high-intensity conditions for nearly five years since opening in December 2021. The operator said the Boten-Vientiane section had also been hit by extreme weather and heavy rain, making a comprehensive overhaul necessary.
It is not the first such campaign on the Laos section. The first concentrated overhaul, from November 2022 to March 2023, involved more than 300 workers, covered over 290 km of track and 179 turnout sets, and improved the track quality index from 5.87 mm to 3.28 mm. The operator expects the current work to raise track quality, passenger comfort and freight efficiency.