Trade, Industry and Energy Minister Kim Jung-kwan said the layout of company fabs at the planned Honam semiconductor cluster will be finalized this month, with an industrial-complex agreement also to be signed in November. He kept the 2030 target for first mass production but acknowledged that land, water and power have not yet been fully secured.
According to the Kyunghyang Shinmun, Kim told the National Assembly's Special Committee on Budget and Accounts on November 10, in response to a question from Democratic Party lawmaker Cho In-cheol about the cluster's schedule, that the layout of companies' fabs is very important and will be wrapped up this month. He called the fab layout the starting point for everything else and said how quickly fabs are completed, together with the Yongin cluster, is directly tied to Korea's chip competitiveness.
광고 문의 · 300×250Under the timeline Kim laid out, an industrial-complex agreement will follow the fab layout this month, fab construction is targeted for 2028-2029 and first mass production for 2030. On the relocation of the Gwangju military airport, whose site is linked to the cluster, work is to begin late this year with the overall outline set next year. Kim said part of the site could see construction before the relocation is complete and that related decisions should also be settled this month.
Kim was cautious about infrastructure. He said infrastructure, water supply and fab layout were progressing quietly behind the scenes, but admitted that land, water and power were not yet 100 percent secured and pledged to move as fast as possible. Asked whether any company had signaled it might pull its investment, he said there had been none at all and that companies want to proceed as quickly as possible. He also noted that memory chip demand had surged since early this year, more than expected.
Kim rejected concerns that the Honam cluster could end up as a subcontracting base for the capital region's chip industry, saying a cluster includes research and development functions as well as production plants. The government presents the project as serving both balanced regional development and the expansion of chip production capacity.
The opposition questioned the pace and the price tag. People Power Party lawmaker Lee Jong-wook said the Lee Jae-myung government was rushing the project, questioned its confidence in the semiconductor cycle, and noted that much of the 94 trillion won total project cost had been exempted from preliminary feasibility studies. Minister of Planning and Budget Park Hong-keun countered that the figure was exaggerated because it includes nationwide projects and items unrelated to semiconductors, such as spending tied to the integration of South Jeolla and Gwangju. Whether the fab layout and complex agreement are confirmed on schedule by month's end will be the first test of the project's momentum.